Bracing for the cold season
Another early round of cool, rainy weather has put a damper on the project. However, the project still remains one week ahead of schedule despite the rain. Block work to tie in the new ambulance garage to the main building was completed during the week of October 19th. Steel workers and welders worked throughout the drizzly to
complete the roof on the new building. The construction crew will continue to prioritize enclosing the building before winter. Concrete for the main floor is scheduled to be poured as soon as the weather permits.
Elsewhere, behind the medical clinic, crews have cleared away trees and the existing picnic shelter roof to make way for the site work needed to be done for the new parking lot. Again, weather permitting, work is moving along to ready the site for a new 40-stall parking lot for BCHC employees. The parking lot will free up the existing Fairview lot, which will be used exclusively for patients and their families. With any luck, the new lot behind the Albion Medical Clinic will be opened in early November.