Archive for February 2010

Feb. 22 Josh Probasco-Superintendent

Update:

We have seen a lot of progress over the last week. 

–O’Hara Plumbing has piping to 75% of the VAV boxes and should be seeing the missing valves by Wednesday of next week.  All VAV boxes should be piped by the end of next week.  Med gas piping will be complete next week.  By March 3rd O’Hara should be off of the first floor and in the basement full time.  There will be guys in the basement to rough in the bathrooms next week as well.

–Middleton Electric has the 480 V feed from the transformer piped (will get measurements and wire to follow) and the emergency feed passed the sidewalk.  They are making arrangements with K & K Construction to come pour back the sidewalk and a few housekeeping pads in the basement.  Middleton has about 20% of the first floor left to tie together above ceiling, and should have this all complete by the end of next week.  There is a crew starting rough-in in the basement. 

–T&H have several finishers on site and plan to have the entire first floor done by March 3rd.  The framers have been working on the stairs and are moving to the basement Monday.  The exterior walls will be framed and insulated next week.  They are going to coordinate their framing with Middleton to get all of the rough-in done in the exterior walls as they go.  EIFS is now complete on the east end of the building (a touch up remains on the north side of the building).

Painter spraying door frames on the east half of the first floor

–Schinstock Painting is now on site.  They sprayed doorframes on the east half of the addition Friday and will prime and first coat those rooms next week.  Schinstock will be on the west half of the first floor immediately following the sheetrock being finished.

–TC Ceilings will be on site March 1st to install ceiling grid in the east half of the building and will be following Schinstock through the west half of the first floor.

–Complete Floors is to be on site March 3rd to begin ceramic tile in the bathrooms

Feb 2nd – Exterior getting completed

The exterior brick is complete and the windows are in place.

Feb 1st – construction progressing

A look down the corridor from the east

Despite weather delays to the project, the work continues.  Sheet rocking is on-going and the basement walls-where the HIM, Purchasing and Central Supply will be located- are going up.  By the end of January all windows in the new addition should be installed.  On the north side of the project, EIFS work is going on under a heated plastic shield. 

  Because the weather has slowed concrete work, the new ambulance garage is now scheduled to be in use the first week of February.  The interior work on the garage is finished and just waiting to be used.

Even with the weather delays, the project is still scheduled to be completed in June 2010.

finish color being applied