Feb 1st – construction progressing
Despite weather delays to the project, the work continues. Sheet rocking is on-going and the basement walls-where the HIM, Purchasing and Central Supply will be located- are going up. By the end of January all windows in the new addition should be installed. On the north side of the project, EIFS work is going on under a heated plastic shield.
Because the weather has slowed concrete work, the new ambulance garage is now scheduled to be in use the first week of February. The interior work on the garage is finished and just waiting to be used.
Even with the weather delays, the project is still scheduled to be completed in June 2010.